LABOR AND MACHINE ASSIGNMENT CALCULATION PROJECT
PROBLEM: Calculate the required labor for past machine
load problems 4 and 6A. For problem 4 assume
the following:
Work two eight hour shifts a day
Absenteeism = 6%
Operators are used elsewhere during DT & SU
Labor efficiency = machine efficiency
Crew sizes for machines I=2, II=3 & III=1
For problem 6A assume the following:
Work one 8 hour shift per day
Absenteeism = 5%
Labor used elsewhere during DT
Labor needed for SU (workers do their own SU)
Labor efficiency = 94%
Crew sizes = 1
REQUIRED: Place all calculations in tabular form
Clearly illustrate and explain each calculation
step for each problem
EVALUATED: Neatness, completeness and accuracy
PROBLEM: Calculate the machine assignments by machine
number for past machine load problems 2, 4 & 5
REQUIRED: Show the total load for each machine
Place all information in tabular form
Clearly illustrate and explain each calculation
step for each problem
EVALUATED: Neatness, completeness and accuracy